NEW ON SITE PALISADE/TIMBER FENCING & GATES
Brief programme of works:
Timber fencing works are now in progress near Parkway House and the northern end of the site. This work is due to complete in Q3 2020.
Steel palisade fencing and gate works are now in progress near the centre of the site, to the rear of units 3, 4 and 5. These works are also due to complete Q3 2020.
MAINTENANCE OF HYDRANT SYSTEM
There are currently maintenance work to the existing hydrant system to the centre/east of the site near the main shed. This work is due to complete mid-autumn.